DRAKE
TECH CENTER - DESIGN/BUILD PROJECT
Fort Collins,
CO
OWNER:
|
JAITUR
Investment, LLLP
3301 E. Prospect Road
Fort Collins, CO 80525 |
|
|
PROJECT
SCHEDULE: |
Design
Start Date: April
1999
Construction Start Date: July 1999
Original Completion Date: December 2000
Actual
Completion Date: January 2000 |
|
|
PROJECT
BUDGET:
|
Contract
Award Amount: $ 3,500,000
Final
Construction Amount: TBD
|
|
|
|
“…your
superintendents and personnel are such a joy to work with…exceptional
performance, knowledge and attitude..!” - Denise Selders
|
|
|
This 35,000 square foot facility incorporates the total Master Builder
concept espoused by MBI (Master Builder International) Corporation.
It culminates several years of this pursuit by Mr. Jairam, president
and CEO of MBI to bring this idea to the forefront of the City of
Fort Collins. This building incorporates state of the art design
and construction methods, including fiber optic networks and unique
concreting techniques. The financing arrangements were also set
up in a unique way by the principals of the development team. |
|